This week has been a relatively quiet week. No heavy building activities.
Chris spent a day in the water supply pit to connect electricity and to put in lights.
We cleaned and cleared the whole back area to be able to mark out the pool.
We needed to set out 1 meter more than the actual pool size to be dug out. Here you see an impression how it is going to be. We went to the pool constructor and chose light green tiles and a soft grey rim around the pool. Exciting!! The offer they had made included a dolphin and a meander rim in tiles as well and we said that we did not want it. It is going to cost the construction company more now because the tile-factory throws in the dolphin and the rim for free! Now they have to buy extra tiles...